Permit guides

Austin Area Permit Guides for Remodeling and Building

What permit each project needs, how to apply, what to submit, what it costs and how to get approved with fewer comments, for Austin, 19 surrounding cities and the unincorporated county land between them, from official sources checked October 18, 2026.

Guides by project

Permit guide

Kitchen Remodel permits

In Austin, a kitchen remodel that keeps walls and plumbing where they are can use an Express Permit, usually issued within a business day.

Read the guide
Permit guide

Bathroom Remodel permits

In Austin, a tub to shower conversion or bathroom refresh that keeps fixtures in place can use an Express Permit.

Read the guide
Permit guide

Whole Home Renovation permits

A whole home renovation in Austin usually needs an Interior Remodel permit (5 business day review) or, if the footprint grows, a New Construction or Addition permit (10 business days), plus electrical, plumbing and mechanical permits pulled by licensed trades.

Read the guide
Permit guide

Home Addition permits

Any home addition in Austin needs a New Construction or Addition permit, with a 10 business day review for each cycle.

Read the guide
Permit guide

ADU (Additional Dwelling Unit) permits

An ADU in Austin is permitted through the New Construction or Addition application, with a 10 business day review.

Read the guide
Permit guide

Garage Conversion permits

Austin reviews garage conversions as a Small Project: the plan review fee is $146.15 and the review takes about 5 business days.

Read the guide
Permit guide

New Garage permits

A new detached or attached garage in Austin goes through the New Construction or Addition application, with a 10 business day review.

Read the guide
Permit guide

Deck and Patio Cover permits

In Austin, a small detached deck is exempt: 200 square feet or less, no more than 30 inches above grade, not attached to the house, not serving as an exit and not in a flood hazard area.

Read the guide
Permit guide

Swimming Pool permits

New pools in Austin use the Pool or Uncovered Deck small project application: $146.15 for plan review and about 5 business days.

Read the guide
Permit guide

New Home permits

A new home in Austin goes through the New Construction or Addition application with a 10 business day review per cycle, plus zoning, utility, tree, fire and, in central Austin, Subchapter F reviews.

Read the guide
Permit guide

Investor and Flip Renovation permits

Flips and rental renovations need the same permits as any remodel, and they run into one problem more often: old work that was never permitted or closed out.

Read the guide

Austin review times

ApplicationReview time
Express Permittypically same day to one business day
Interior Remodel5 business days
Small Project (garage conversion, pool or uncovered deck, fence)5 business days
New Construction or Addition10 business days
Total Demolition5 business days
Update submittal after comments7 business days

Source: City of Austin Residential Plan Review, review times effective July 1, 2026.

How permitting works in Austin

  • Prepare the application, checklist documents and plans for your project type
  • Check the property's permit history and file an Acknowledgment of Expired Permits if needed
  • Submit through the residential building permit web form; the city invoices the review fee and review starts once it is paid
  • Answer any comments in the Master Comment Report and resubmit the full plan set
  • Once approved, the registered contractor activates the permit in the Austin Build + Connect (AB+C) portal and schedules inspections

Austin rules worth knowing

  • Homeowners can act as their own general contractor and, on their own homestead, pull electrical, plumbing and mechanical permits, except for the main electric service, refrigerant work on ducted systems, LP gas and auxiliary water systems.
  • The city does not inspect residential foundations; a registered design professional's report confirming the foundation must be provided at the final inspection.
  • Insulation cannot be installed until the framing inspection is approved.
  • A permit expires on the 181st day if no inspection has been scheduled or received.
  • Trees 19 inches or more in diameter on or next to the lot trigger tree review; floodplain review applies within 100 feet of the 100 year floodplain; historic review applies to houses 45 years or older when the exterior is demolished or modified.
  • New dwelling units can owe Austin Water capital recovery (impact) fees, set by meter size and the plat date.

Austin builds to the 2024 International Residential Code with City of Austin local amendments, effective July 10, 2025. Read the full Austin permit guide.

Getting approved with fewer comments

Check the permit history first

Search the property on the City of Austin Public Search. If old permits expired, file the Acknowledgment of Expired Permits with your application; unresolved permits are a common reason for delays.

Know which rules apply to the lot

Use the city's Property Profile to see zoning, Subchapter F (the residential design standards that set height and setback planes in much of central Austin), floodplain and historic status. Floodplain review is required within 100 feet of the 100 year floodplain.

Check deed restrictions and the HOA yourself

The city does not enforce private deed restrictions; the applicant is responsible for them, and HOA approval is a separate step.

Make the floor plans complete

The city lists what reviewers look for: scale, room labels and square footage, wall dimensions, ceiling heights, door and window sizes, smoke and carbon monoxide alarm locations, plumbing fixtures, and handrail and guardrail locations, with existing and proposed plans when anything changes.

Get the structural documents right

New construction needs foundation, wind bracing and framing plans. For some projects, such as interior remodels without additions, a Structural Verification Report from an engineer can be used instead.

Deal with trees up front

Trees 19 inches or more in diameter on or next to the lot trigger tree review. Locating them on the site plan before design avoids redesigns later.

Submit clean files

The city recommends vector based PDFs and requires one combined PDF; partial or informal updates are not accepted.

Answer every comment precisely

Respond to each comment in writing, say where and how it was addressed with the code section, cloud the changes, and resubmit the full plan set after paying any generated fees. The fee schedule lists a residential resubmittal fee of $585.77, so a complete first submittal saves money as well as time.

Ask before you submit

A Preliminary Plan Review meeting (consultation fee $409.38 for the first hour) can settle zoning or design questions before review starts. Reviewers are not available by phone, email or appointment on Fridays.

Permits by city

Every city in the metro runs its own portal, adopts its own code editions and sets its own fees. Each city guide lists where to apply, the adopted codes, published review times and fees, local rules and the official sources.

CityWhere to applyReview time
AustinAustin Build + Connect (AB+C)Express about one business day; interior remodels and small projects 5 business days; new construction and additions 10 business days; updates 7 business days (from July 1, 2026)
Round RockCity of Round Rock permit portalAbout 30 business days for a single family remodel after the application is accepted; no expedited review
Cedar ParkMGO ConnectNot published; ask Building Inspection
GeorgetownMGO ConnectNot published; ask Building Inspections
PflugervillePublic Access Permitting PortalNot published; ask Building Inspection and Permits
LeanderDevelopment HubAbout 10 days for the first review of an addition or remodel; about 5 days per review for pools
HuttoCity of Hutto building permitsNot published; ask Building & Code Enforcement
ManorMyPermitNow (GovWell), since May 27, 2026Not published
LakewayCivic Self ServiceNot published
Bee CaveCity of Bee Cave Building Permits & InspectionsNot published
West Lake HillsCity of West Lake Hills Building & DevelopmentNot published; the development coordinator can say whether a pre-application meeting is needed
Dripping SpringsCity of Dripping Springs Building DepartmentNot published
KyleCitizen Self-Service (CSS) portalNot published
BudaCity of Buda Building Codes & InspectionsTypically 10–15 business days, with more rounds if there are compliance issues
San MarcosMGO ConnectNot published
Liberty HillCity of Liberty Hill Building Permits & InspectionsNot published
TaylorCity of Taylor Building PermitsNot published
BastropCity of Bastrop Building & PermittingNot published
LockhartCity of Lockhart Development ServicesNot published
Marble FallsCity of Marble Falls Building DivisionNot published

Outside city limits: Travis County, Williamson County, Hays County, Bastrop County and Caldwell County permits for unincorporated land.

Outside city limits

Texas counties generally do not issue building permits, but they do issue development, floodplain and septic (OSSF) permits, and some require a county permit number before any other approval.

Texas licensing for remodeling trades

WhoWhat Texas requires
General contractorsTexas has no state license for general contractors; cities register contractors locally (Austin, Cedar Park and Marble Falls, for example).
ElectriciansElectrical work requires a license from the Texas Department of Licensing and Regulation (apprentice, residential wireman, journeyman or master, working under a licensed electrical contractor).
PlumbersPlumbing work requires registration or a license from the Texas State Board of Plumbing Examiners (apprentice, tradesman, journeyman or master).
Air conditioning and refrigerationTDLR registers technicians, certifies technicians who pass an exam, and licenses contractors, who need 48 months of experience and an exam. Registered technicians work under a licensed contractor. Handling refrigerant also requires EPA Section 608 certification.
HomeownersMany cities let homeowners pull permits for their own homestead. In Austin that includes electrical, plumbing and mechanical work, with exceptions such as the main electric service and refrigerant work.

Sources: TDLR: Air Conditioning and Refrigeration Contractors; TDLR: Electricians; Texas State Board of Plumbing Examiners; City of Austin Homeowner's Permit.

Frequently asked questions

How long does a residential permit take in Austin?

Since July 1, 2026, the City of Austin's stated review times are about one business day for Express Permits, 5 business days for interior remodels and small projects such as garage conversions, pools and decks, and 10 business days for new construction and additions. Each update after comments takes another 7 business days.

How much are permit fees in Austin?

Plan review fees start at $112.76 for an Express Permit and $146.15 for a small project. Addition and remodel review fees grow with square footage, and new construction review starts at $986.15. Building, electrical, mechanical and plumbing inspection permits are charged separately.

Who can pull a permit in Austin?

A general contractor registered with the city, or a homeowner acting as their own general contractor. Electrical, mechanical and plumbing permits are pulled by licensed, registered trade contractors.

This guide is general information gathered from official city sources on October 18, 2026. Rules and fees change, usually each October; we confirm them for your address during the free consultation.

Let us handle the permits